71504 decided approve with conditions Last updated 21/07/2025, 13:44

Consultation from Rochdale Council for a scoping opinion on building up to 21 wind turbines, each up to 180m tall, with a total generating capacity of 100MW3, including infrastructure, access, and restoration of degraded peat moorland.

Consultation From Neighbouring Authority

Rochdale, OL12 8XL

OL12 8XL

Full Proposal

Article 18 Consultation from Rochdale Council (ref:24/01241/SCO) for proposed request for scoping opinion in respect of the erection of up to 21 wind turbines up to 180m in height with a generating capacity of 100MW3 with associated infrastructure and access, including restoration and enhancement of degraded peat moorland

Application Timeline

Application Registered
07/01/2025
Application Validated
07/01/2025
Target Decision Date
28/01/2025
Committee Date
N/A
Decision Made
27/01/2025
Decision Issued
27/01/2025

Case Officer

Applicant

Development Management - Rochdale MBC

More Information